Repair of Opel Corsa C, from 2000 to 2005 of release.
1. Operation and car maintenance
2. Engine
3. Transmission
3.1. Coupling
3.2. Mechanical box передч
3.3. Automatic transmission
3.3.1. General information
3.3.2. Hydrotransformer
3.3.3. Main transfer
3.3.4. Adjustment of a cable of the selector of switching of automatic transmission
3.3.5. Designation of an automatic transmission (AF 13-II)
3.3.6. Check of a condition of transmission oil (AF13-II)
3.3.7. Check of pressure of oil (AF13-II)
3.3.8. Check of the item switch of the lever of gear shifting (AF13-II)
3.3.9. Unblocking of a stopper of the lever of gear shifting at violation of its work
3.3.10. Adjustment of the item switch of the lever of gear shifting (AF13-II)
3.3.11. Adjustment of hummock system of a drive of gear shifting (AF13-II)
3.3.12. Replacement of hummock system of a drive of gear shifting (AF13-II)
3.3.13. Replacement of the switch of the lock adaptation of the lever of gear shifting
3.3.14. Replacement of a plait of wires in knot of the lever of gear shifting (AF13-II)
3.3.15. Replacement of the control unit of the check point electronic switch
3.3.16. Replacement of the filament lamp of the indicator of gear shifting in the console of the lever of gear shifting (AF 13-II)
3.4. Driving mechanism
4. Running gear
5. Steering mechanism
6. Brake system
7. Onboard electric equipment
8. Body
9. Electric equipment schemes
 








99e20293



3-3-15-zamena-bloka-upravleniya-ehlektronnogo-pereklyuchatelya-kpp.html

3.3.15. Replacement of the control unit of the check point electronic switch

NOTE
At control unit replacement before demontazhy make dumping of data by the TECH2 device.

Disconnect clips of the storage battery.
Release and disconnect the socket of a plait of wires 1 and 3.
Wring out outside fixing ledges 2 and take out forward the check point control unit.

NOTE
Depending on option of the engine and a check point differently calibrated check points control units are applied. At replacement of the check point control unit use the corresponding new block. It is ordered in the service center.

Fix the check point control unit in the holder.
Insert and fix 2 sockets of plaits of wires.
Attach clips of the storage battery.
Program volatile memories.

NOTE
At control unit replacement, after control unit installation, execute the appropriate program by means of the device.

«on page back